Projects and money

Money announced is not money spent, and spent is not delivered. Each stage is shown separately.

Portsmouth International Port — cruise and ferry terminal

Complete Published figures City-wide
Committed
£11.25m
Spent to date
£11.25m
Accountable body
Portsmouth City Council (port is council-owned)
Next decision
None outstanding — operational
Announced
Evidenced
Funding awarded
Evidenced
Money received
Not published
Council decision
Not published
Contracted
Not published
Spent
Evidenced
Delivered
Evidenced
Outcome measured
Not published
Detail and source

The only Levelling Up component with an independently published figure: the port states on its own site that the terminal was made possible through £11.25m of Levelling Up funding, matching the capital programme. Opened to first passengers 20 August 2023. The council’s 2024/25 accounts describe it as fully operational, handling an additional 250,000 passengers a year.

Funder: Levelling Up Fund Round 1

Source

Linear Park and Hilsea Lido

Underway Reconstructed figures Portsmouth North
Committed
£7.75m grant (scheme total since risen to £8.286m)
Spent to date
£4.85m to March 2025
Accountable body
Portsmouth City Council
Next decision
Completion of the wider linear park beyond the Lido itself
Announced
Evidenced
Funding awarded
Evidenced
Money received
Not published
Council decision
Not published
Contracted
Not published
Spent
Evidenced
Delivered
Not published
Outcome measured
Not published
Detail and source

The council’s Winter 2025 Flagship magazine, page 26, states £7.6m for the lido renovation. The retained capital-programme reconstruction gives £7.75m for the wider Linear Park grant line; these are different scopes and have not been reconciled. The lido reopening does not establish completion of the whole Linear Park programme.

Funder: Levelling Up Fund Round 1, plus £486k council contribution

Delay: About a year. The contractor said in June 2024 it would complete in spring 2025 for the summer season; it opened 2 May 2026.

Source

Football facilities — Levelling Up attribution unconfirmed

Unverified Inferred figures City-wide
Committed
Historic £1m capital line; Levelling Up attribution unconfirmed
Spent to date
No verified project-specific Levelling Up spend
Accountable body
Portsmouth City Council
Next decision
Obtain a project-specific funding and completion record.
Announced
Evidenced
Funding awarded
Not published
Money received
Not published
Council decision
Not published
Contracted
Not published
Spent
Not published
Delivered
Not published
Outcome measured
Not published
Detail and source

The retained capital-programme reconstruction identifies a £1m football-facilities line. This review has not verified a project-specific official link to the Levelling Up award or a named completed facility. The government’s £20m award total does not prove the attribution of this line. It is excluded from confirmed Levelling Up grant and spend totals here; the historic reconstruction remains available in the original snapshot.

Funder: Not verified for this project

Source

Hilsea Lines moat restoration and sea defences

Underway Published figures Portsmouth North
Committed
Not published as a single figure
Spent to date
Not published
Accountable body
Coastal Partners with the Environment Agency and Portsmouth City Council
Next decision
Completion of sea-defence work, end of 2026
Announced
Evidenced
Funding awarded
Not published
Money received
Not published
Council decision
Not published
Contracted
Not published
Spent
Not published
Delivered
Not published
Outcome measured
Not published
Detail and source

Commonly and wrongly attributed to the £20m Levelling Up award. The scheme’s own site attributes it to funding secured by the environment team for 2025/26 and does not identify it as Levelling Up money anywhere. Dredging began September 2025. Crediting a flood-defence scheme to a regeneration grant makes that grant look like it delivered more than it did.

Funder: North Portsea Coastal Scheme Phase 5 — Environment Agency and Coastal Partners

Source

Southsea Coastal Scheme

Underway Published figures Portsmouth South
Committed
See scheme site
Spent to date
Not published as a running total
Accountable body
Coastal Partners / Portsmouth City Council
Next decision
Successive frontage phases through to completion
Announced
Evidenced
Funding awarded
Not published
Money received
Not published
Council decision
Not published
Contracted
Not published
Spent
Not published
Delivered
Not published
Outcome measured
Not published
Detail and source

The largest local authority-led flood defence scheme in England, protecting around 10,000 homes and businesses. Rebuilding the seafront public realm as it goes, which is why it also appears in regeneration discussion.

Funder: Environment Agency flood defence grant in aid, with partnership funding

Source

City Centre North — former Tricorn and Sainsbury’s sites

Allocated in Local Plan Published figures Portsmouth South
Committed
At least £16.1m of land assembly
Spent to date
At least £16.1m spent on acquisitions
Accountable body
Portsmouth City Council (landowner and planning authority)
Next decision
Check the published decision and conditions for application 22/01243/CS3, then the funded delivery stages.
Announced
Evidenced
Funding awarded
Evidenced
Money received
Not published
Council decision
Not published
Contracted
Not published
Spent
Evidenced
Delivered
Not published
Outcome measured
Not published
Detail and source

October 2026 council examination evidence identifies application 22/01243/CS3 for phased development of up to 2,300 homes and non-residential space. An application or masterplan is not proof of permission, construction or completed homes. The retained land-acquisition figures describe a different stage and retain their original review date.

Funder: Portsmouth City Council capital — land assembly. A development partner is still required for the scheme itself

Source

Tipner West

Allocated in Local Plan Published figures Portsmouth North
Committed
No public funding committed
Spent to date
n/a
Accountable body
Portsmouth City Council
Next decision
Local Plan examination
Announced
Evidenced
Funding awarded
Not published
Money received
Not published
Council decision
Not published
Contracted
Not published
Spent
Not published
Delivered
Not published
Outcome measured
Not published
Detail and source

Housing alongside marine employment space. The sequencing matters: if housing is built first and employment space last, the employment element is the part most at risk of never arriving. That risk is this site’s analysis, not council policy.

Funder: To be determined

Source

As of 15 September 2026. Stage uses five levels deliberately: complete, underway, funded but not started, allocated in the Local Plan, and proposed. Allocation is the level most often reported as though it were delivery. Confidence is separate: "Published" means the figure appears in a public document; "Reconstructed" means it was assembled from a capital programme rather than stated; "Inferred" means the attribution is our judgement and could be wrong.

LonglistedUK City of Culture 2029 bidShortlist due autumn 2026; winner January 2027